Lisbon — Halquist Stone Co. reopened Lisbon Road (Highway K) several days ahead of schedule April 28, despite several delays caused by utility company work on the road and inclement weather.
The road had been closed for 68 days to allow the company to build an underpass connecting its south and north quarries. Halquist staff will continue working on the project for the next few weeks to create berms and plant large trees for a more natural appearance along the underpass and the roadside above.