City of Oconomowoc - The Wisconsin Avenue reconstruction will recommence Monday, April 21, announced officials of the Wisconsin Department of Transportation and Dorner Inc.
The news came during the weekly construction update meeting at the Community Center Wednesday morning.
To catch up on lost time, officials said there will be an acceleration of the work schedule meaning crews will work 15 to 16 hours a day on a seven day work week.
Expectations are to complete the stretch of road from Fowler Street to Main Street in time for the Festival of the Arts Aug. 16 and 17.
The remaining stretches of road will then follow.
The original completion date was scheduled for Sep.1 in most areas.